CameraIcon
CameraIcon
SearchIcon
MyQuestionIcon
MyQuestionIcon
1
You visited us 1 times! Enjoying our articles? Unlock Full Access!
Question

10 boys can dig a pitch in 12 hours. How long will 8 boys take to do it?
(a) 9 hrs 36 min
(b) 15 hrs
(c) 6 hrs 40 min
(d) 13 hrs 10 min

Open in App
Solution

(b) 15 hrs
Time taken by 10 boys to dig a pitch = 12 hours
Time taken by 1 boy to dig a pitch = 12 × 10 = 120 hours (Less boys would take more hours.)
Time taken by 8 boys to dig a pitch = 120 = 15 hours
8

flag
Suggest Corrections
thumbs-up
0
Join BYJU'S Learning Program
similar_icon
Related Videos
thumbnail
lock
Speed-Distance-Time
QUANTITATIVE APTITUDE
Watch in App
Join BYJU'S Learning Program
CrossIcon