Question

12 men complete a work in 9 days. After they have worked for 6 days, 6 more men join them. How many days will they take to complete the remaining work ?

A
2 days
Right on! Give the BNAT exam to get a 100% scholarship for BYJUS courses
B
3 days
No worries! We‘ve got your back. Try BYJU‘S free classes today!
C
4 days
No worries! We‘ve got your back. Try BYJU‘S free classes today!
D
5 days
No worries! We‘ve got your back. Try BYJU‘S free classes today!
E
None of these
No worries! We‘ve got your back. Try BYJU‘S free classes today!
Open in App
Solution

The correct option is A 2 days
12 men 9 days Let 36 unit be worked to complete
12 men 369 unit/day
= 4 unit/day 1 Men = 13 unit/ day
for 6 Men 2 unit / Day
24 unit
Left work 3624=12 unit
Now total Men= 12 M +6M = 18 M
18 M compete the work in a day = 3618=2 days

1201053_1296981_ans_3fcff98dda774bec927b9cdc6211dc56.jpg

flag
Suggest Corrections
thumbs-up
1
Join BYJU'S Learning Program
similar_icon
Related Videos
thumbnail
lock
Introduction to Direct Proportions
MATHEMATICS
Watch in App
Join BYJU'S Learning Program
CrossIcon