Question

$$15$$ men can build a wall in $$60$$ days. How many more men are required to build another wall of same size in $$45$$ days?


A
2 men
loader
B
7 men
loader
C
5 men
loader
D
3 men
loader

Solution

The correct option is C $$5$$ men
Let $$x$$ men are required to build the wall in $$45$$ days.
Then $$x:15::60:45$$
$$\Rightarrow 45x=15\times 60$$
$$\Rightarrow x=\dfrac{15\times 60}{45}$$
$$x=20$$ men.
Hence, $$20-15=5 $$ more men are required.