A alone can do a piece of work in 10 days and B alone can do the same work in 15 days. They started working together. After two days, both of them left the work. If C alone can complete the remaining work in 5 days, then in how many days can C alone complete the work?

A
8.5 days
No worries! We‘ve got your back. Try BYJU‘S free classes today!
B
7.5 days
Right on! Give the BNAT exam to get a 100% scholarship for BYJUS courses
C
7 days
No worries! We‘ve got your back. Try BYJU‘S free classes today!
D
8 days
No worries! We‘ve got your back. Try BYJU‘S free classes today!
E
None of these
No worries! We‘ve got your back. Try BYJU‘S free classes today!
Open in App
Solution

The correct option is B 7.5 days
Total work = L.C.M of 10 and 15 = 30 units

As 1day work=3010=3 units

Bs 1day work=3015=2 units

(A + B)’s 1-day work = 3 + 2 = 5 units

Now (A + B)’s 2-day work = 2×5=10 units

Remaining work = 30 – 10 = 20 units

20 units of work done by C in 5 days

30 units of work done by C in 520×30=7.5 days.

So, C alone can complete the whole work in 7.5 days

flag
Suggest Corrections
thumbs-up
0
Join BYJU'S Learning Program
similar_icon
Related Videos
thumbnail
lock
Cel & Mia at Wonderla
MATHEMATICS
Watch in App
Join BYJU'S Learning Program
CrossIcon