CameraIcon
CameraIcon
SearchIcon
MyQuestionIcon
MyQuestionIcon
1
You visited us 1 times! Enjoying our articles? Unlock Full Access!
Question

A and B can do a piece of work in 30 days, while B and C can do the same work in 24 days and C and A in 20 days. They all work together for 10 days when B and C leave. How many days more will A take to finish the work?

A
18 days
Right on! Give the BNAT exam to get a 100% scholarship for BYJUS courses
B
24 days
No worries! We‘ve got your back. Try BYJU‘S free classes today!
C
30 days
No worries! We‘ve got your back. Try BYJU‘S free classes today!
D
36 days
No worries! We‘ve got your back. Try BYJU‘S free classes today!
Open in App
Solution

The correct option is A 18 days
2(A+B+C)'s 1 day's work =(130+124+120)=15120=18.
Therefore, (A+B+C)'s 1 day's work =12×8=16.
Work done by A,B,C in 10 days =1016=58
Remaining work =(158)=38.
A's 1 day's work =(116124)=148.
Now, 18 work done by A in 1 day.
So, 38 work will be done by A in (48×38)=18 days.

flag
Suggest Corrections
thumbs-up
1
Join BYJU'S Learning Program
similar_icon
Related Videos
thumbnail
lock
Time and Work
MATHEMATICS
Watch in App
Join BYJU'S Learning Program
CrossIcon