A and B can finish a piece of work in 16 days and 12 days respectively. A started the work and worked at it for 2 days. He was then Joined by B. Find the total time taken to finish the work.
A's one day's work =116
B's one day's work =112
A and B's one day's work =116+112
=3+448=748
A's 2 days work =116×2=18
Remaining work =1−18=78
∴ A and B will finish the 78 work in
=78×487=6 days
∴ Whole work will be finished in 2+6 =8 days