A and B together can do a piece of work in 12 days; B and C can do it in 20 days while C and A can do it in 15 days. A,B and C all working together can do it in
A
6 days
No worries! We‘ve got your back. Try BYJU‘S free classes today!
B
9 days
No worries! We‘ve got your back. Try BYJU‘S free classes today!
C
10 days
Right on! Give the BNAT exam to get a 100% scholarship for BYJUS courses
D
101/2 days
No worries! We‘ve got your back. Try BYJU‘S free classes today!
Open in App
Solution
The correct option is C10 days We know that,
Number of days required by A and B to complete the work =12 days
Number of days required by B and C to complete the work =20 days
Number of days required by C and A to complete the work =15 days
∴ We can calculate, work done by A and B in 1 day =1/12
Work done by B and C in 1 day =1/20
Work done by C and A in 1 day =1/15
Now, work done by (A and B), (B and C), (C and A) together in 1 day is given by
The sum is (A+B)+(B+C)+(C+A)=2(A+B+C)=1/12+1/20+1/15=12/60=1/5