Question

A and B together can do a piece of work in 12 days; B and C can do it in 20 days while C and A can do it in 15 days. A,B and C all working together can do it in

A
6 days
No worries! We‘ve got your back. Try BYJU‘S free classes today!
B
9 days
No worries! We‘ve got your back. Try BYJU‘S free classes today!
C
10 days
Right on! Give the BNAT exam to get a 100% scholarship for BYJUS courses
D
101/2 days
No worries! We‘ve got your back. Try BYJU‘S free classes today!
Open in App
Solution

The correct option is C 10 days
We know that,
Number of days required by A and B to complete the work =12 days

Number of days required by B and C to complete the work =20 days

Number of days required by C and A to complete the work =15 days

We can calculate, work done by A and B in 1 day =1/12
Work done by B and C in 1 day =1/20
Work done by C and A in 1 day =1/15

Now, work done by (A and B), (B and C), (C and A) together in 1 day is given by
The sum is (A+B)+(B+C)+(C+A)=2(A+B+C)=1/12+1/20+1/15=12/60=1/5
Hence.
Work done by A,B,C=1/2×1/5=1/10

A,B,C can do the work in 10 days.

flag
Suggest Corrections
thumbs-up
0
Join BYJU'S Learning Program
similar_icon
Related Videos
thumbnail
lock
Time and Work
MATHEMATICS
Watch in App
Join BYJU'S Learning Program
CrossIcon