CameraIcon
CameraIcon
SearchIcon
MyQuestionIcon
MyQuestionIcon
1
You visited us 1 times! Enjoying our articles? Unlock Full Access!
Question

A can do a piece of work in 15 days. 13 is 50% more efficient than A. B can finish it in

(a) 10 days

(b) 712 days

(c) 12 days

(d) 1012days

Join BYJU'S Learning Program
CrossIcon