A can do a piece of work in 24 days. If B is 60% more efficient then the number of days required by B to do the twice as large as the earlier work is-

A
24
No worries! We‘ve got your back. Try BYJU‘S free classes today!
B
36
No worries! We‘ve got your back. Try BYJU‘S free classes today!
C
15
No worries! We‘ve got your back. Try BYJU‘S free classes today!
D
30
Right on! Give the BNAT exam to get a 100% scholarship for BYJUS courses
Open in App
Solution

The correct option is D 30
According to the question-
A can do a piece of work in 24 days.
work done by A in 1 day =124
Given that, B is 60% more efficient, i.e., B can do 60% more work than work done by A in 1 day-
Work done by B in 1 day =124+60100×124=115
number of days required by B to do the same work =15days
number of days required by B to do the twice as large as the earlier work =2×15=30 days

flag
Suggest Corrections
thumbs-up
0
Join BYJU'S Learning Program
similar_icon
Related Videos
thumbnail
lock
The First Law of Thermodynamics
PHYSICS
Watch in App
Join BYJU'S Learning Program
CrossIcon