CameraIcon
CameraIcon
SearchIcon
MyQuestionIcon
MyQuestionIcon
1
You visited us 1 times! Enjoying our articles? Unlock Full Access!
Question

A can do 14 of a work in 5 days and B can do 13 of the same work in 10 days . Find the number of days in which both working together will complete the work .

A
12 days
Right on! Give the BNAT exam to get a 100% scholarship for BYJUS courses
B
20 days
No worries! We‘ve got your back. Try BYJU‘S free classes today!
C
44 days
No worries! We‘ve got your back. Try BYJU‘S free classes today!
D
18 days
No worries! We‘ve got your back. Try BYJU‘S free classes today!
Open in App
Solution

The correct option is A 12 days
A can do the complete work in 5×4=20 days
B can do the complete work in 10×3=30 days
Here X =20, Y =30
A and B , working together , can complete the work in =XYX+Y days
=20×3020+30=60050=12 days

flag
Suggest Corrections
thumbs-up
2
Join BYJU'S Learning Program
similar_icon
Related Videos
thumbnail
lock
Ratio and Proportion
MATHEMATICS
Watch in App
Join BYJU'S Learning Program
CrossIcon