Consider the following data regarding an activity AB:
Earliest start time = 3 days
Earliest finish time = 8 days
Latest start time = 5 days
Latest finish time = 10 days
Then interfering float for this activity is ______________days .
2
Open in App
Solution
The correct option is A 2 Activitytime=EFT−ESTorLFT−LST
= 8 - 3 or 10 - 5
= 5 days
Interfering float = Total float - Free float
Total float = LST - EST
=5 - 3
= 2 days
Free float = EFT - EST - Activity time
=8 - 3- 5
= 0 days
\therefore\) Interfering float = FT−FF
= 2-0
= 2 days