How many worker are required for completing the construction work in 10 days?
I. 20% of the work can be completed by 8 workers in 8 days.
II. 20 workers can complete the work in 16 days.
III. One-eighth of the work can be completed by 8 workers in 5 days.

A
I only
No worries! We‘ve got your back. Try BYJU‘S free classes today!
B
II and III only
No worries! We‘ve got your back. Try BYJU‘S free classes today!
C
III only
No worries! We‘ve got your back. Try BYJU‘S free classes today!
D
I and III only
No worries! We‘ve got your back. Try BYJU‘S free classes today!
E
Any one of the three
Right on! Give the BNAT exam to get a 100% scholarship for BYJUS courses
Open in App
Solution

The correct option is E Any one of the three
I. 20100 work can be completed by (8×8) workers in 1 day.
Whole work can be completed by (8×8×5) workers in 1 day.
=8×8×510 workers in 10 days =32 workers in 10 days.
II. (20×16) workers can finish it in 1 day.
(20×16)10 workers can finish it in 10 days.
32 workers can finish it in 10 days.
III. 18 work can be completed by (8×5) workers in 1 day.
Whole work can be completed by (8×5×8) workers in 1 day.
=8×5×810 workers in 10 days =32 workers in 10 days.
Any one of the three gives the answer.
Correct answer is (E).

flag
Suggest Corrections
thumbs-up
0
Join BYJU'S Learning Program
similar_icon
Related Videos
thumbnail
lock
Time and Work
MATHEMATICS
Watch in App
Join BYJU'S Learning Program
CrossIcon