CameraIcon
CameraIcon
SearchIcon
MyQuestionIcon
MyQuestionIcon
1
You visited us 1 times! Enjoying our articles? Unlock Full Access!
Question

If 20 men working 7 hours a day can do a piece of work in 10 days, in how many days will 15 men working 8 hours a day do the same piece of work ?

A
15521
No worries! We‘ve got your back. Try BYJU‘S free classes today!
B
1123
Right on! Give the BNAT exam to get a 100% scholarship for BYJUS courses
C
6916
No worries! We‘ve got your back. Try BYJU‘S free classes today!
D
415
No worries! We‘ve got your back. Try BYJU‘S free classes today!
Open in App
Solution

The correct option is B 1123
20 men working 7 hours a day can complete the work in 10 days
20 men working 1 hour a day can complete the work in (10 x 7) days (Less hours More days)
1 man working 1 hour a day can complete the work in ( 10 x 7 x 20) days (Less men More days)
1 man orking 8 hours a day can complete the work in =(10×7×20)8×15 days (More men Less days)
(Less men More days) = =353 days = 1123 days

flag
Suggest Corrections
thumbs-up
0
Join BYJU'S Learning Program
similar_icon
Related Videos
thumbnail
lock
Time and Work
MATHEMATICS
Watch in App
Join BYJU'S Learning Program
CrossIcon