Question

If 36 workers can build a wall in 12 days, how many days will 16 workers take to build the same wall? (Assuming the number of working hours per day is constant)

Open in App
Solution

If the number of workers decreases, the time to taken built the wall increases in the same proportion. Clearly, number of workers varies inversely to the number of days.
So here x1y1=x2y2 where
x1=36 workers y1=12 days
x2=16 workers and y2=? days
Substitute, 3616=y212 y2=12×3616=27 days
Therefore 16 workers will build the same wall in 27 days.