If 6 men and 8 boys can do a piece of work in 10 days while 26 men and 48 boys can do the same in 2 days, the time taken by 15 men and 20 boys in doing the same type of work will be
4 days
Let1 man's 1 day's work = x and 1 boy's 1 day's work = y
Then, 6x+8y =110 and 26x + 48y =12
Solving these two equations, we get: x = 1100 and y = 1200
(15 men + 20 boy)'s 1 day's work =[15100+20200]=14
15 men and 20 boys can do the work in 4 days