If the optimistic time, most likely time and pessimistic time for activity A are 7, 8 and 9 days respectively and for activity B are 6, 7.5 and 12 days respectively, then :

A
Expected time of both the activities A and B will be same
Right on! Give the BNAT exam to get a 100% scholarship for BYJUS courses
B
Expected time of activity B is greater than the expected time of activity A
No worries! We‘ve got your back. Try BYJU‘S free classes today!
C
Expected time of activity A is greater than the expected time of activity B
No worries! We‘ve got your back. Try BYJU‘S free classes today!
D
None of the above
No worries! We‘ve got your back. Try BYJU‘S free classes today!
Open in App
Solution

The correct option is A Expected time of both the activities A and B will be same
For activity A

to=7 days

tm=8 days

tp=9 days

Expected time=t0+4tm+tp6

=7+4×8+96=8 days

For activity B

to=6 days

tm=7.5 days

tp=12 days

Expected time=6+4×7.5+126

=8 days

Hence, the expected time of both activity A and B will be the same.

flag
Suggest Corrections
thumbs-up
1
Join BYJU'S Learning Program
similar_icon
Related Videos
thumbnail
lock
Sum of n Terms of an AP
MATHEMATICS
Watch in App
Join BYJU'S Learning Program
CrossIcon