CameraIcon
CameraIcon
SearchIcon
MyQuestionIcon


Question

Karan can do a piece of work in 8 days, whereas Sarosh can do the same in 4 days. They were made to work together and completed the work in ‘x’ days which is 103 days before the deadline given to them. In how many days were they supposed to complete the work?


  1. 6

  2. 3

  3. 5

  4. 7

  5. 4


Solution

The correct option is A

6


Work done by Karan in a day = 18

Work done by Sarosh in a day = 14

Work done by Karan and Sarosh together in a day = 18+14

=38

Time taken by them to complete the work = 83 days

Time given to them = 6 days.

flag
 Suggest corrections
thumbs-up
 
0 Upvotes


Similar questions
QuestionImage
QuestionImage
View More...



footer-image