On a certain assembly line, the rejection rate for Monday's production was 4%, for Tuesday it was 8% and for the two days combined 7%. What was the ratio of Tuesday's production to Monday's production?


  1. 3:1

  2. 2:1

  3. 1:3

  4. 1:2


Solution

The correct option is A

3:1