CameraIcon
CameraIcon
SearchIcon
MyQuestionIcon
MyQuestionIcon
1
You visited us 1 times! Enjoying our articles? Unlock Full Access!
Question

P, Q and R can do a work in 12, 24 and 32 days respectively. They all begin together. P continues to work till it is finished. R left after 4 days and Q one and half day before its completion. In what time is the work finished?


A

10.5 days

No worries! We‘ve got your back. Try BYJU‘S free classes today!
B

7.5 days

Right on! Give the BNAT exam to get a 100% scholarship for BYJUS courses
C

152 days

Right on! Give the BNAT exam to get a 100% scholarship for BYJUS courses
D

12 days

No worries! We‘ve got your back. Try BYJU‘S free classes today!
Join BYJU'S Learning Program
CrossIcon