Sharma is 20% less efficient than Kelkar. If Kelkar can do a piece of work in 24 days, then the number of days required by Sharma to complete the same work alone.

A
20
No worries! We‘ve got your back. Try BYJU‘S free classes today!
B
30
Right on! Give the BNAT exam to get a 100% scholarship for BYJUS courses
C
28.8
No worries! We‘ve got your back. Try BYJU‘S free classes today!
D
can't be determined
No worries! We‘ve got your back. Try BYJU‘S free classes today!