Question

The mass of a bucket containing water is 10 kg. What is the work done in pulling up the bucket from a well of depth 10 m if water is pouring out at a uniform rate from a hole in it and there is loss of 2kg of water from it while it reaches the top (g=10m/sec2)


A

1000 J

No worries! We‘ve got your back. Try BYJU‘S free classes today!
B

800 J

No worries! We‘ve got your back. Try BYJU‘S free classes today!
C

900 J

Right on! Give the BNAT exam to get a 100% scholarship for BYJUS courses
D

500 J

No worries! We‘ve got your back. Try BYJU‘S free classes today!
Open in App
Solution

The correct option is C

900 J


Gravitational force on bucket at starting position =mg=10×10=100N

Gravitational force on bucket at final position =8×10=80N

So the average force through out the vertical motion =100+802=90N

Work done =Force×displacement=90×10=900J


flag
Suggest Corrections
thumbs-up
0
Join BYJU'S Learning Program
similar_icon
Related Videos
thumbnail
lock
The Work Done as a Dot-Product
PHYSICS
Watch in App
Join BYJU'S Learning Program
CrossIcon