The optimistic, most likely and expected completion time of an activity are 4 days, 11 days and 10 days respectively. The pessimistic time of this activity will be________ days.
12
Open in App
Solution
The correct option is A 12 Expected time, tc=t0+4tm+tp6 ⇒10=4+4×11+tp6
So, tp=12 days