What is meant by the 'follow-up action' as the step involved in the process of planning



A

Checking whether the activities are performed according to the manager. 

loader
B

Checking whether the activities are performed during the peak hours of the day. 

loader
C

Checking whether the activities are performed according to the plan and the schedule or not. 

loader
D

None of the above

loader

Solution

The correct option is A

Checking whether the activities are performed according to the plan and the schedule or not. 


In the process of planning, follow-up action means checking, whether the activities are performed according to the plan and the schedule or not. 