CameraIcon
CameraIcon
SearchIcon
MyQuestionIcon
MyQuestionIcon
1
You visited us 1 times! Enjoying our articles? Unlock Full Access!
Question

X can do a piece of work in 25 days and Y can finish it in 20 days. They work together for 5 days and then X leaves. In how many days will Y finish the remaining work ?

Open in App
Solution

Let the total work be 1
Then, According to question X takes 25 days to do 1 work.
Then work done by X in 1 day=125

Also according to question Y takes 20 days to do 1 work.
Then work doe by Y in 1 day=120

Then total work done by both of them in 1 day =120+125=9100
Then total work done by both of them 5 days=45100
Then total work left =145100=55100
Now, As Y can do 1 work in 25 days therefore,
Y can do 55100 work in 55100×25 days
=554 days

flag
Suggest Corrections
thumbs-up
2
Join BYJU'S Learning Program
similar_icon
Related Videos
thumbnail
lock
Time and Work
MATHEMATICS
Watch in App
Join BYJU'S Learning Program
CrossIcon