A contract on construction job specifies a penalty for delay of completion beyond a certain date as follows: Rs. 200 for the first day, Rs. 250 for the second day, Rs. 300 for the third day, etc., the penalty for each succeeding day being Rs. 50 more than for the preceding day. How much money the contractor has to pay as penalty, if he has delayed the work by 30 days.

Given that

The penalty for each succeeding day being Rs. 50 more than for the preceding day.

Find out

We have to find out how much money the contractor has to pay as penalty, if he has delayed the work by 30 days.

Solution

The given penalties are in the form of A.P. having first term as 200 and common difference as 50.

Hence, a = 200 and d = 50

Penalty that has to be paid if contractor has delayed the work by 30 days = S30

By the formula of sum of nth term, we know,

Sn = n/2[2a+(n -1)d]

Therefore,

S30= 30/2[2(200)+(30 – 1)50]

= 15[400+1450]

= 15(1850)

= 27750

Answer

Therefore, the contractor has to pay Rs 27750 as penalty.

Was this answer helpful?

  
   

0 (0)

Upvote (0)

Choose An Option That Best Describes Your Problem

Thank you. Your Feedback will Help us Serve you better.

Leave a Comment

Your Mobile number and Email id will not be published. Required fields are marked *

*

*

BOOK

Free Class

Ask
Question