Deviations are said to be positive in nature when _____.


A

Planned performance is more than the actual performance.

No worries! We‘ve got your back. Try BYJU‘S free classes today!
B

Actual performance is more than the planned performance.

Right on! Give the BNAT exam to get a 100% scholarship for BYJUS courses
C

Both planned and actual performances are the same.

No worries! We‘ve got your back. Try BYJU‘S free classes today!
D

None of the above.

No worries! We‘ve got your back. Try BYJU‘S free classes today!
Open in App
Solution

The correct option is B

Actual performance is more than the planned performance.


Answer (b) Actual performance is more than the planned performance.

Explanation: Actual performance is a crucial piece of checking an association’s advancement. It includes estimating the actual performance results or consequences of an association against its expected objectives. If the performance can be quantified, it becomes easier to measure actual performance. When the actual performance is more than the planned performance, it becomes a positive deviation while measuring the performance.


flag
Suggest Corrections
thumbs-up
0
Join BYJU'S Learning Program
similar_icon
Related Videos
thumbnail
lock
Importance of Controlling
BUSINESS STUDIES
Watch in App
Join BYJU'S Learning Program
CrossIcon