1 h triangular unit hydrograph of a watershed has the peak discharge of 60 m3/s at 10 h and time base of 30h. The ϕindex is 0.4 cm/h and base flow is 15 m3/s

If there is rainfall of 5.4 cm in 1 hour the ordinate of the flood hydrograph at 15th hour is

A
225 m3/s
No worries! We‘ve got your back. Try BYJU‘S free classes today!
B
240 m3/s
Right on! Give the BNAT exam to get a 100% scholarship for BYJUS courses
C
249 m3/s
No worries! We‘ve got your back. Try BYJU‘S free classes today!
D
258 m3/s
No worries! We‘ve got your back. Try BYJU‘S free classes today!
Open in App
Solution

The correct option is B 240 m3/s

Rainfall in 1 h = 5.4 cm
Effective rainfall in 1 h
=5.4ϕ=5.40.4=5 cm

Ordinate of flood hydrograph = 5 [ordinate of UH at 15th hour] + base flow
=5×45+15=240 m3/s

flag
Suggest Corrections
thumbs-up
6
similar_icon
Similar questions
View More
Join BYJU'S Learning Program
similar_icon
Related Videos
thumbnail
lock
Introduction and Basic Assumptions of Unit Hydrograph
HYDROLOGY & IRRIGATION
Watch in App
Join BYJU'S Learning Program
CrossIcon