10 boys can dig a pitch in 12 hours. How long will 8 boys take to do it?
(a) 9 hrs 36 min
(b) 15 hrs
(c) 6 hrs 40 min
(d) 13 hrs 10 min

Open in App
Solution

(b) 15 hrs
Time taken by 10 boys to dig a pitch = 12 hours
Time taken by 1 boy to dig a pitch = 12 × 10 = 120 hours (Less boys would take more hours.)
Time taken by 8 boys to dig a pitch = 120 = 15 hours
8