10 men can reap a field in 20 days. 10 men reaped the field for 10 days and after 10 days 10 more men join them. In how many days will the work be finished?
15 days
Total number of work days required =10 x 20 = 200
Since 10 men worked for 10 days, 10 x 10 = 100 days work is already done.
So, 200 - 100 = 100 days of work is left.
Once, 10 more men joined, total number of workers=20
So, number of days required more =10020=5
Thus, total number of days = 10 + 5 = 15.