10 women can complete a work in 7 days and 10 children take 14 days to complete the work. How many days will 5 women and 10 children take to complete the work?
7
1 woman 1 day’s work =170
1 child 1 day’s work =1140
(5 women + 10 children)’s 1 day’s work =(570+10140)=(114+114)=17
∴ The total work will be completed in 7 days.