12 children take 16 days to complete a work which can be completed by 8 adults in 12 days. 16 adults started working and after 3 days, 10 adults left and 4 children joined them. How many days will they take to complete the remaining work ?
A
3
No worries! We‘ve got your back. Try BYJU‘S free classes today!
B
4
No worries! We‘ve got your back. Try BYJU‘S free classes today!
C
6
Right on! Give the BNAT exam to get a 100% scholarship for BYJUS courses
D
8
No worries! We‘ve got your back. Try BYJU‘S free classes today!
Open in App
Solution
The correct option is B6 12 children take 16 days to complete a work
8 adults take 12 days to complete the same job.
Let the productivity of children be c and the productivity of adult be m
Thus,
12c×16=8m×12
=>c=12m
Work done by 8 men in 12 days 8m×12=96m
Work done by 16 men in 3 days =16m×3=48m
Work left =96m−48m=48m
After 3 days 10 adults left and 4 children joined them
Thus, 6 men and 4 children have to complete the remaining job.