12 men can complete a piece of work in 16 days. How many days will 4 men take to complete the task?

A
60 days
No worries! We‘ve got your back. Try BYJU‘S free classes today!
B
45 days
No worries! We‘ve got your back. Try BYJU‘S free classes today!
C
54 days
No worries! We‘ve got your back. Try BYJU‘S free classes today!
D
48 days
Right on! Give the BNAT exam to get a 100% scholarship for BYJUS courses
Open in App
Solution

The correct option is C 48 days
1 man will complete the job in 16×12 days.
So, 4 will do in 12×164=48 days.