12 men complete a work in 20 days If only 8 men are emplited, then the time required to complete the same work is
A
24days
No worries! We‘ve got your back. Try BYJU‘S free classes today!
B
25days
No worries! We‘ve got your back. Try BYJU‘S free classes today!
C
30days
Right on! Give the BNAT exam to get a 100% scholarship for BYJUS courses
D
35days
No worries! We‘ve got your back. Try BYJU‘S free classes today!
Open in App
Solution
The correct option is B 30days 12 men completed the work in 20 days ∴ One man can complete the same work in 12×20 days So 8 men will complete the same work in 12×208=30days