12 men working 8 hours a day complete a work in 10 days. How long would 16 men working 7 12 hours a day take to complete the same work ?
Open in App
Solution
Let the work completed in x days. MensHoursDays1281016152x
More men less time , Less men more time. Thus it is inverse variation 12:16::152×x:8×10 ⇒x=10×12×8×216×15=8 ⇒16 men will complete the same work in 8 days.