12 persons can dig 324 cubic meters earth in a day. How many person will be required to dig 270 cubic meters earth ?

Open in App
Solution

To dig 324 cubic meters earth in a day, required number of persons =12
Thus, to dig 270 cubic meters earth in a day, required number of persons =12×270324
=10 persons