CameraIcon
CameraIcon
SearchIcon
MyQuestionIcon
MyQuestionIcon
53
You visited us 53 times! Enjoying our articles? Unlock Full Access!
Question

12 persons can dig 324 cubic meters earth in a day. How many person will be required to dig 270 cubic meters earth ?

Open in App
Solution

To dig 324 cubic meters earth in a day, required number of persons =12
Thus, to dig 270 cubic meters earth in a day, required number of persons =12×270324
=10 persons

flag
Suggest Corrections
thumbs-up
0
Join BYJU'S Learning Program
similar_icon
Related Videos
thumbnail
lock
Time and Work
MATHEMATICS
Watch in App
Join BYJU'S Learning Program
CrossIcon