15.300 workers were engaged to finish a piece of work in a certain number of days. If 8 workers dropped on the second day, 8 more workers dropped on the third day and so on. It took 8 more days to finish the work now. The number of days in which the work was completed is 1. 35 2. 30 3. 25 4. 28