175 men can dig a canal 3150 m long in 36 days. How many men are required to dig a canal 3900 m long in 24 days?


A

256

No worries! We‘ve got your back. Try BYJU‘S free classes today!
B

225

No worries! We‘ve got your back. Try BYJU‘S free classes today!
C

325

Right on! Give the BNAT exam to get a 100% scholarship for BYJUS courses
D

384

No worries! We‘ve got your back. Try BYJU‘S free classes today!
Open in App
Solution

The correct option is C

325


No.of menLengthNo.of days175315036X390024

We'll define a new variable
Number of man days (N)

N=No. of men×No of days

N1=175×36=6300

N2=X×24=24X

Let length of the canal dug be L

Number of man days is directly proportional to the length of the canal dug.

N1N2=L1L2

630024X=31503900

X=390012=325

Hence, 325 men are required to dig a length of 3900m in 24 days.


flag
Suggest Corrections
thumbs-up
3
Join BYJU'S Learning Program
similar_icon
Related Videos
thumbnail
lock
Inverse Variations
MATHEMATICS
Watch in App
Join BYJU'S Learning Program
CrossIcon