2 men and 7 women can do a piece of work in 4 days, while 4 men and 4 women can do the same work in 3 days . How many would it take one men and one women to do it ?
Step 1 :Assigning the variables
To represent the unknown quantities by two variables.
let 1st man finish the work in x days and 1 woman in y days
Therefore , 1 man's 1 days work = 1/x
and 1 woman one days work = 1/y
Step 2: Framing Equation
According to the question
Step 3 : Elimination method
Solving with suitable method (elimination)
Multiplying equation (1) by (2) ,
It becomes
Subtracting equation 2 from equation 3 we get
Step 4 : Substituting values
substitute the value of y = 60 in equation 1
we get ,
Hence ,1st man can finish the work in 15 days and 1st woman can finish the work in 60 days .