wiz-icon
MyQuestionIcon
MyQuestionIcon
1
You visited us 1 times! Enjoying our articles? Unlock Full Access!
Question

20 labour can dig a pond in 12 days. How many days will it take 16 laborers to dig the same pond?

Open in App
Solution

Solution:-
Let the no. of days take by 16 labour to dig the same pond be x.
Given that no. of days taken by 20 labour to dig a pond =12
work done by 20 labour in 12 days = work done by 16 labour in x days
20×12=16×x
x=20×1216=15
Hence, 16 labour will dig the same pond in 15 days.

flag
Suggest Corrections
thumbs-up
2
Join BYJU'S Learning Program
similar_icon
Related Videos
thumbnail
lock
Solving Linear Equations
MATHEMATICS
Watch in App
Join BYJU'S Learning Program
CrossIcon