210 men working 12 hours a day can finish a job in 18 days. How many men are required to finish the job in 20 days working 14 hours a day?

Open in App
Solution

Let the required number of men be x.

More working hours = less men required.
It is inverse proportion.
Multiplying factor is 1214
Also more number of days = less men
It is an inverse proportion
Multiplying factor is 1820
x=210×1214×1820
210×12×1814×20x=162men
162 men are required.