25 boys can complete a piece of work in 6 days. In how many days will 75 men complete the same work?

A
2 days
Right on! Give the BNAT exam to get a 100% scholarship for BYJUS courses
B
4 days
No worries! We‘ve got your back. Try BYJU‘S free classes today!
C
8 days
No worries! We‘ve got your back. Try BYJU‘S free classes today!
D
16 days
No worries! We‘ve got your back. Try BYJU‘S free classes today!
Open in App
Solution

The correct option is A 2 days
The number of boys (B) required to complete a work is directly proportional to the amount of work (W).

B W...(1)

The number of boys (B) required to complete a work is inversely proportional to the number of days required to do the work (D).

B1D...(2)

Combining (1) and (2), we get,

BWD

Let k be the constant of variation.
So, B=kWD

BDW=K(constant)

Let the number of days required to complete the same work by 75 boys be x days.

Hence, (25)(6)W =(75)(x)W

150=75x
So,x=2 days

flag
Suggest Corrections
thumbs-up
0
Join BYJU'S Learning Program
similar_icon
Related Videos
thumbnail
lock
Inverse Proportions
MATHEMATICS
Watch in App
Join BYJU'S Learning Program
CrossIcon