Question

25 men were employed to do a piece of work in 24 days. After 15 days, 10 more men were engaged and the work was finished a day soon. In what time could they finish the work if extra men were not employed?

Open in App
Solution

Actual work done =(25×15)+(25+10)×8=655 man days
Time required by 25 men to complete this work is =65525=26.2 days