Pradeep receives an export order for garments. He has machines to complete the order in days. How many machines would be required to complete the job in days?
Step1: Finding he job to be completed on day
The number of machines is inversely proportioned to the number of days
days machines
day machines
Step2: Finding the job to be completed in days
day machines
days machines
machines are needed to complete the job in days.