Question

Question 88

30 persons can reap a field in 17 days. How many more persons should be engaged to reap the same field in 10 days?

Open in App
Solution

Since, 30 persons can reap a field in 17 days.
1 person can reap the same field in 30×17 i.e. 510 days
In 10 days the number of persons required =51010=51persons