Given that,
Let number of men’s (M1)=30
Number of days=(D1)=17
Again Here, the work done is same field for 10 days
Then, number of men’s(M2)=?
Number of days(D2)=10
Now, we know that,
M1×D1=M2×D2
30×17=M2×10
⇒M2=30×1710
⇒M2=3×17
⇒M2=51
Hence, 51 more persons should be engaged to reap the same field in 10 days.