30 persons can reap a field in 17 days.How many more persons should be engaged to reap the same field in 10 days?

Open in App
Solution

Given that,

Let number of men’s (M1)=30

Number of days=(D1)=17

Again Here, the work done is same field for 10 days

Then, number of men’s(M2)=?

Number of days(D2)=10

Now, we know that,

M1×D1=M2×D2

30×17=M2×10

M2=30×1710

M2=3×17

M2=51

Hence, 51 more persons should be engaged to reap the same field in 10 days.