39 men can build a bridge in 12 days, working 5 hours a day. In how many days will 30 men, working 6 hours a day, complete the work?
A
10
No worries! We‘ve got your back. Try BYJU‘S free classes today!
B
13
Right on! Give the BNAT exam to get a 100% scholarship for BYJUS courses
C
14
No worries! We‘ve got your back. Try BYJU‘S free classes today!
D
15
No worries! We‘ve got your back. Try BYJU‘S free classes today!
Open in App
Solution
The correct option is B 13 MandaysQuantity of work=39×12××5=2340 We know number of men is inversely proportinal to number of days, so =2340=30×6× number of days =2340=180× number of days =2340180= number of days 13= number of days