39 people can repair a road in 12 days, working 5 hours a day. In how many days will 30 people working 6 hours a day complete the work?
Open in App
Solution
Let the number of days required for 30 people working 6 hours a day be x.
Number of people
Time taken (in hours)
39
12×5 = 60
30
x×6 = 6x
Time taken and number of people are in inverse variation.
So, using arrow method: 3930=6x60
On cross multiplication, x=3930×606=13
So, the required number of days is 13.