wiz-icon
MyQuestionIcon
MyQuestionIcon
1
You visited us 1 times! Enjoying our articles? Unlock Full Access!
Question

39 people can repair a road in 12 days, working 5 hours a day. In how many days will 30 people working 6 hours a day complete the work?

Open in App
Solution

Let the number of days required for 30 people working 6 hours a day be x.
Number of people Time taken (in hours)
39 12×5 = 60
30 x×6 = 6x
[1 Mark]
Time taken and number of people are in inverse variation.
So, using arrow method:
3930=6x60
On cross multiplication,
x=3930×606=13
So, the required number of days is 13. [2 Marks]

flag
Suggest Corrections
thumbs-up
0
Join BYJU'S Learning Program
similar_icon
Related Videos
thumbnail
lock
Introduction to Direct Proportions
MATHEMATICS
Watch in App
Join BYJU'S Learning Program
CrossIcon