Question
4 men and 4 boys can do a piece of work in 3 days. While 2 men and 5 boys can finish in 4 days. How would it take for 1 boy to do it? How long would it take to 1 men do it?
Open in App
Solution
Let a boy do xth function of work in one day and a man yth function